Re: C4 Production Question
Floyd -
I think the date you see on the build sheet is the date the order was accepted by the plant for production and the sheet was formatted (and the material requirements were forecast/transmitted), not the date it was printed. There were printers all over the plant (mostly in subassembly areas that fed the main line in sequence), and the build sheets that were actually used on the line were usually printed less than an hour before they were needed.
Floyd -
I think the date you see on the build sheet is the date the order was accepted by the plant for production and the sheet was formatted (and the material requirements were forecast/transmitted), not the date it was printed. There were printers all over the plant (mostly in subassembly areas that fed the main line in sequence), and the build sheets that were actually used on the line were usually printed less than an hour before they were needed.
Comment