67 - Tank Sticker versus Body Build Date Question - NCRS Discussion Boards

67 - Tank Sticker versus Body Build Date Question

Collapse
X
 
  • Time
  • Show
Clear All
new posts
  • Douglas L.
    Very Frequent User
    • August 31, 2003
    • 299

    67 - Tank Sticker versus Body Build Date Question

    What is the relationship between the "expected date of production" as shown on the 67 tank stickers versus the body build date as shown on the 67 trim tags? Here are three documented examples:

    67 - 427 - Body build date: 8/31/66 - Tank Sticker Expected date of production: 9/14/66 - St. Louis
    67 - 427 - Body build date: 9/16/66 - Tank Sticker Expected date of production: 9/30/66 - St. Louis
    67 - 427 - Body build date: 3/03/67 - Tank Sticker Expected date of production: 3/03/67 - St. Louis
    67 - 327 - Body build date: 2/16/67 - Tank Sticker Expected date of production: 3/03/67 - A.O. Smith

    It appears from the above examples the time difference between the body build date and the expected date of production could vary by as much as two weeks and then at other times be the same. Was there flux in the time period between body build date and expected date of production or is there a time period that would be considered normal?
  • Robert G.
    Expired
    • May 31, 1990
    • 429

    #2
    Re: 67 - Tank Sticker versus Body Build Date Question

    Originally posted by Douglas Lee (40617)
    What is the relationship between the "expected date of production" as shown on the 67 tank stickers versus the body build date as shown on the 67 trim tags? Here are three documented examples:

    67 - 427 - Body build date: 8/31/66 - Tank Sticker Expected date of production: 9/14/66 - St. Louis
    67 - 427 - Body build date: 9/16/66 - Tank Sticker Expected date of production: 9/30/66 - St. Louis
    67 - 427 - Body build date: 3/03/67 - Tank Sticker Expected date of production: 3/03/67 - St. Louis
    67 - 327 - Body build date: 2/16/67 - Tank Sticker Expected date of production: 3/03/67 - A.O. Smith

    It appears from the above examples the time difference between the body build date and the expected date of production could vary by as much as two weeks and then at other times be the same. Was there flux in the time period between body build date and expected date of production or is there a time period that would be considered normal?
    I would be highly suspicious of any expected date of production before 9/30/66, so the first one raises a red flag for me. I keep track of data like this but I don't have any easy way to cross reference what you're asking for. I would say there is no relationship between body build date and EDP.
    A better thing to compare is VIN and EDP or Body build date and VIN.
    I keep track of VIN/EDP and can tell you that there is a spread of thousands of vins that share the same EDP.

    Comment

    • Patrick T.
      Expired
      • September 30, 1999
      • 1286

      #3
      Re: 67 - Tank Sticker versus Body Build Date Question

      Here is the tank sticker for my '67 L-79. The expected date of production in 6-30-67. The VIN is 22526, so it is a very late '67.

      Comment

      • John D.
        Very Frequent User
        • June 30, 1991
        • 875

        #4
        Re: 67 - Tank Sticker versus Body Build Date Question

        Wasn't there a strike In St. Louis on the september-october 1966 timeframe ?

        Comment

        • Wayne M.
          Expired
          • March 1, 1980
          • 6414

          #5
          Re: 67 - Tank Sticker versus Body Build Date Question

          With the exception of your first car in the list, with EDP 9/14/66, all 3 others have EDP's that fall on a Friday, including Patrick's example. Apparently this was the rule; maybe John H. knows why.

          Comment

          • Leif A.
            Extremely Frequent Poster
            • August 31, 1997
            • 3626

            #6
            Re: 67 - Tank Sticker versus Body Build Date Question

            Originally posted by Patrick Tighe (33001)
            Here is the tank sticker for my '67 L-79. The expected date of production in 6-30-67. The VIN is 22526, so it is a very late '67.

            I guess I'm easily amused but I always get a kick out of the A82 option on '67 Corvettes - Headrests Bench Seat
            Leif
            '67 Coupe L79, M21, C60, N14, N40, J50, A31, U69, A01, QB1
            Top Flight 2017 Lone Star Regional

            Comment

            • Larry M.
              Extremely Frequent Poster
              • January 1, 1992
              • 2688

              #7
              Re: 67 - Tank Sticker versus Body Build Date Question

              Originally posted by Wayne Midkiff (3437)
              With the exception of your first car in the list, with EDP 9/14/66, all 3 others have EDP's that fall on a Friday, including Patrick's example. Apparently this was the rule; maybe John H. knows why.
              Wayne:

              I believe that all 1967 tank stickers have an Estimated Production Date (EPD) that is a Friday. That was one way of finding reproduction or fraudulent tank stickers in the early years. Now just about everyone knows that. I guess back then they couldn't estimate production any tighter than a week or so. The time between the Order Date and the EPD was typically around 6 weeks, if I remember correctly.

              IN GENERAL, the actual build date of the car is +/- about 2 weeks (or so) from this EPD. Some cars are earlier than the EPD, but many are later. A few hit the date exactly. Special options (like headrests or tele steering, etc can cause the actual build date to be much later than the EPD due to unavailability of these parts at that specific time.

              Obviously, production work stoppages (strikes) can also play a part in all of this…….and some of that did occur late in 1966.

              The body build date is another issue. Generally speaking, St Louis built bodies became a finished car on the same day or 1-2 days later (weekend/holiday issues) than the day the body was finished. AOS built bodies became a finished car about 7-14 days after the body was built. This is due to rail transportation time from AOS to St Louis.

              All my statements above are for the 1967 model year only. I do not have information for the other (later) C3 years. Take it for what it's worth.

              Larry
              Last edited by Larry M.; February 7, 2015, 10:50 PM.

              Comment

              • John H.
                Beyond Control Poster
                • December 1, 1997
                • 16513

                #8
                Re: 67 - Tank Sticker versus Body Build Date Question

                Cars weren't built until the material (parts) required for that particular car were in-house or reliably in-transit. When the plant accepted the dealer order for production, they assigned the Ident Number and the EDP; the EDP was simply a projection of 4 weeks (give or take a week or two) to procure and receive the material, which was ordered in 500-unit schedule blocks. When that schedule's material was on hand, Production Control configured that 500-unit schedule to fit their needs and released it to the production floor.

                Comment

                • Michael J.
                  Extremely Frequent Poster
                  • January 27, 2009
                  • 7119

                  #9
                  Re: 67 - Tank Sticker versus Body Build Date Question

                  You learn something new every day, never knew about the projections and Friday EDP before, fits with my tank sticker too.
                  Big Tanks In the High Mountains of New Mexico

                  Comment

                  • Harry S.
                    Extremely Frequent Poster
                    • July 31, 2002
                    • 5293

                    #10
                    Re: 67 - Tank Sticker versus Body Build Date Question

                    John's answer fits earlier C2's. My 63 EDP was Friday 4/26/63. The actual build date was Saturday 4/20/63. Well it was probably second shift of 4/19/63 just after midnight making it Saturday.


                    Comment

                    • David H.
                      Extremely Frequent Poster
                      • June 30, 2001
                      • 1525

                      #11
                      Re: 67 - Tank Sticker versus Body Build Date Question

                      Originally posted by Larry Mulder (20401)
                      Wayne:
                      ... All my statements above are for the 1967 model year only. I do not have information for the other (later) C3 years. Take it for what it's worth.

                      Larry
                      FWIW: my 1980 has a trim tag date of 1 April (yes, I know April Fools!), with a DATE of 2 April (Wednesday) on the tank build sheet. The Shipper Document as well, shows both the "Invoiced Date" and the "Shipped Date" as 2 April. At some point the default Friday EPDs changed.
                      Judging Chairman Mid-Way USA (Kansas) Chapter

                      Comment

                      • Douglas L.
                        Very Frequent User
                        • August 31, 2003
                        • 299

                        #12
                        Re: 67 - Tank Sticker versus Body Build Date Question

                        John,

                        So, a question for you. On car one below, the "order date" was 7/21/66 which fits what you say about the window of time between the order date and the EDOP. However, on the third car below, the "order date" was 10/13/66 and the EDOP was not until 3/3/67. Could a car get held up being produced for lack of a "particular" part so that it would push the EDOP out that far? Car #3 is a California A.I.R. car which represented about 11% of production.

                        67 - 427 - Body build date: 8/31/66 - Tank Sticker Expected date of production: 9/14/66 - St. Louis - Order Date: 7/21/66
                        67 - 427 - Body build date: 9/16/66 - Tank Sticker Expected date of production: 9/30/66 - St. Louis
                        67 - 427 - Body build date: 3/03/67 - Tank Sticker Expected date of production: 3/03/67 - St. Louis - Order Date: 10/13/66
                        67 - 327 - Body build date: 2/16/67 - Tank Sticker Expected date of production: 3/03/67 - A.O. Smith - Order Date: 2/2/67

                        Comment

                        • John H.
                          Beyond Control Poster
                          • December 1, 1997
                          • 16513

                          #13
                          Re: 67 - Tank Sticker versus Body Build Date Question

                          Originally posted by Douglas Lee (40617)
                          John,

                          So, a question for you. On car one below, the "order date" was 7/21/66 which fits what you say about the window of time between the order date and the EDOP. However, on the third car below, the "order date" was 10/13/66 and the EDOP was not until 3/3/67. Could a car get held up being produced for lack of a "particular" part so that it would push the EDOP out that far? Car #3 is a California A.I.R. car which represented about 11% of production.
                          Doug -

                          Yes, any number of things could push the EDOP further down the calendar, from a change in the dealer order to an incompatible option combination the Zone order edit didn't catch, to the dealer going out of trust with GMAC, to the dealer exceeding his order allocation, to a supplier part shortage, to a transportation failure, etc. There were lots of reasons why cars didn't get built as originally projected.

                          Comment

                          • Tom R.
                            Extremely Frequent Poster
                            • June 30, 1993
                            • 4099

                            #14
                            Re: 67 - Tank Sticker versus Body Build Date Question

                            Originally posted by David Houlihan (36425)
                            FWIW: my 1980 has a trim tag date of 1 April (yes, I know April Fools!), with a DATE of 2 April (Wednesday) on the tank build sheet. The Shipper Document as well, shows both the "Invoiced Date" and the "Shipped Date" as 2 April. At some point the default Friday EPDs changed.
                            Not to hijack the original discussion thread but a number of practices changed how information was used by the late 1970s and/or late model C3s from the early C3s or the late 1960s. The intent of the EDOP, set by Zone, was to inform the dealer of the expected date when production would begin and notify the plant of an order. Changes included:

                            1. General Motors Acceptance Division took over management of the Corvette plant in the early 1970s.
                            2. This resulted in the GMAD landscape buildsheet adopted in 1973, accompanied with greater attention to production data driving assembly process
                            3. During the late to mid 1970s, greater attention to engineering process incorporated into the production process
                            4. Dramatic production increases from less than 30k units to nearly 50k units required more efficient processes to be instituted

                            I just posted this in a recent forum discussion but this table illustrates the differentials between pairs of VINs versus their associated EDOP, taken from the buildsheet and associated job number. The data is based on 1978 Pace Cars where data is plentiful to study the association between numbers. By 1978, the plant was using projected schedule data. Schedule data incorporated the EDOP and the job number and the schedule number. It shows assignment of VIN tags on contrast to the EDOP, documented from the build sheet.

                            Table1.gif
                            Tom Russo

                            78 SA NCRS 5 Star Bowtie
                            78 Pace Car L82 M21
                            00 MY/TR/Conv

                            Comment

                            Working...
                            Searching...Please wait.
                            An unexpected error was returned: 'Your submission could not be processed because you have logged in since the previous page was loaded.

                            Please push the back button and reload the previous window.'
                            An unexpected error was returned: 'Your submission could not be processed because the token has expired.

                            Please push the back button and reload the previous window.'
                            An internal error has occurred and the module cannot be displayed.
                            There are no results that meet this criteria.
                            Search Result for "|||"