When I did mine five years ago (44' x 58'), we laid a 10-mil poly moisture barrier first, then laid 4' x 8' sheets of 1/2"-thick tongue-and-groove high-density closed-cell foam with heavy foil on both sides on top of the poly before setting the mesh and pouring the slab; ZERO moisture migration, good insulation - it's always warm and dry.
When I did mine five years ago (44' x 58'), we laid a 10-mil poly moisture barrier first, then laid 4' x 8' sheets of 1/2"-thick tongue-and-groove high-density closed-cell foam with heavy foil on both sides on top of the poly before setting the mesh and pouring the slab; ZERO moisture migration, good insulation - it's always warm and dry.